Not to follow the date sequence for the activities entered in the deductions table in laytime calculation. Instead, follow the sequence of activities entered by the user.

Example:
User add First activity - 'From Date/Time' as 19/03/21 05:50
User add Second activity - 'From Date/Time' as 19/03/21 04:00
As soon as the user key in the second activity 'From date/time' earlier than the first activity 'From date/time', the second activity will shift to the line 1 and it will hard for the user to identify which activity he/she was entering.

Under consideration demurrage Suggested by: Roshanthi Upvoted: 04 May, '21 Comments: 0